Maldives Resort Island 1.1 MWp Solar-Storage Microgrid
Summary: Renewable energy share raised to 68%, diesel consumption down 64%.
The resort island's electrical load varies widely between day and night, and the existing diesel generation was costly to run. The project deployed 1.1 MWp of PV and 2.5 MWh of energy storage, together with hybrid inverters and an EMS.
Results
- Renewable energy share reached 68%
- Diesel consumption down 64%
- Payback period of about 4.5 years
Selection and implementation notes
- Fix the converter rating from the continuous load and the overload factor before sizing the battery for the required autonomy.
- Keep the EMS point table, firmware revision and wiring diagram under change control to avoid commissioning delays.
- Verify the on/off-grid transfer time, the STS sequence and the protection settings with event logs and waveform captures.
- Decide which unit forms the grid: island and weak-grid sites need a grid-forming PCS or a VSG to establish voltage and frequency.
Related products and resources
SP250HAG2T、LEONA-M200K(SP200HAPV)、LEONA-B750K(SP750H54PSTD) · technical guides · categories
Frequently asked questions
Does this project need a grid-forming PCS?
Island sites, weak grids, black-start duty and diesel coordination call for a grid-forming converter. A stiff grid with grid-tied-only operation can use a grid-following unit.
FAQ
How can VGRID POWER support "Maldives Resort Island 1.1 MWp Solar-Storage Microgrid"?
VGRID POWER focuses on microgrid and storage core equipment — PCS, STS, AC microgrid cabinets and hybrid inverters — with end-to-end support from design and EMS to OEM/ODM.
How to size PCS power and battery capacity?
Base it on load, peak/valley tariff, PV capacity and backup duration. VGRID POWER offers 30kVA–2MW PCS and cabinets with EMS-based economic dispatch.
How to get a design and quotation?
Contact us via the website form or email for a free assessment, datasheets and quotation; OEM/ODM and custom integration supported.