Wenzhou Industrial Park 1.2 MWh user-side energy storage
Results
- ¥620kAnnual bill saving
- 2 cycles/dayPeak-valley arbitrage
- −22%Demand reduction
Summary: Two charge and two discharge cycles per day, annual electricity cost savings of approximately RMB 620,000, and a 22% reduction in maximum demand.
Manufacturing enterprises in the park show a clear peak-valley price spread. After deploying 600 kW/1.2 MWh user-side energy storage, the system performs two charge and two discharge cycles per day, automatically executing peak-valley arbitrage.
Operating Results
- Two charge and discharge cycles per day
- 22% reduction in maximum demand
- Annual electricity cost savings of approximately RMB 620,000
The EMS coordinates with the park's existing distribution system to enable capacity expansion without production stoppage.